Design Your Home

Build it on screen
before we build it on your lot.

Walk through the same choices we'd make together at your kitchen table — size, foundation, roof, materials, finishes. There are no packages here and nothing is bundled: mix anything with anything. At the end you'll see roughly how long your build takes and what drives it.

Build Time

Why some homes take
longer than others.

Nobody sets out to build slowly. But a few decisions quietly add weeks or months, and most builders won't tell you which ones until you're already committed. Here's the honest list.

01

What's under the house

A slab goes in fast. A full basement means excavation, footings, walls, waterproofing, and backfill — and concrete cures on its own schedule no matter how badly everyone wants it to hurry. A walkout on a sloped lot adds more still. Basements are worth it for a lot of families. Just know you're buying weeks along with the square footage.

02

What's holding up the roof

Standard trusses are engineered, built, and delivered on a predictable schedule. Ask for vaulted ceilings, an attic-truss bonus room, or a roofline with several gables running into each other, and those trusses become a custom order — extra engineering, extra approval, extra build time at the plant before anything shows up on your lot.

03

Your cabinets, honestly

This is the one that surprises people. Amish hand-built cabinetry is the reason a Legacy kitchen looks the way it does — and full custom takes a couple of months to build once the order is placed. That clock starts when you finalize the selections, not when we frame the house. Decide early and it never costs you a day.

04

What your land needs

A lot with city water and sewer at the road is the fast path. Raw acreage may need clearing, a long driveway, a well, and a septic system — and septic starts with a soil evaluation that can take weeks just to get scheduled, before anyone applies for a permit. We walk your lot early precisely so this never becomes a surprise.

05

When you start

Breaking ground in late fall means pouring concrete and framing through an Ohio winter. It's absolutely doable — we build year-round — but cold slows curing and weather steals days. A spring start usually runs the cleanest schedule of the year.

06

How fast you decide

The single biggest thing under your control. Every selection left open is a decision that eventually has to happen anyway, only later — and by then it's holding up an order that holds up a trade that holds up your move-in. We'll give you a deadline for each one so nothing sits.